Visualized: What Does It Cost to Build and Run a Data Center?

What does a data center cost? Explore the costs of an AI facility and see why servers dominate annual spending.

This story was prepared automatically by software.

Visualized: What Does It Cost to Build and Run a Data Center?

Published

November 27, 2026 11:12 am

By

Ryan Bellefontaine

The following content is sponsored by The National Public Utilities Council

Breaking Down the Cost of an AI Data Center

Key Takeaways

  • Servers account for nearly 60% of the modeled annual cost of a 1-GW AI data center.

  • Annualized capital costs greatly exceed annual operating expenses.

  • Energy is the largest operating expense, but accounts for only about 7% of the modeled annual total.

As AI infrastructure expands, the cost of building a data center is becoming as important as the electricity needed to run it. Advanced computing equipment, facilities, and networking all contribute to the bill.

This graphic, in partnership with the National Public Utilities Council, compares annualized building costs with operating expenses for a hypothetical 1-GW AI data center, using data from Epoch AI.

The Cost of Building Versus Running a Data Center

Epoch AI estimates nearly $38 billion in up-front investment for the modeled facility. To compare that investment with yearly expenses, the study spreads capital costs across assumed asset lifespans and financing costs.

The table below breaks down annualized capital costs and operating expenses, in millions of U.S. dollars.

Cost typeCost componentAnnual cost (US$M)

BuildServers5,021

BuildFacility1,387

BuildNetwork infrastructure1,167

BuildUtility works20

BuildLand13

RunEnergy594

RunTaxes143

RunMaintenance120

RunLabor40

RunWater6

Methodology

×

Methodology

Figures model a hypothetical AI data center with 1 GW of IT power using NVIDIA GB200 NVL72 systems. Capital costs are annualized using assumed asset lifespans and financing; actual costs may vary.

Servers represent the largest component at $5.02 billion annually. Facility costs follow at $1.39 billion, while networking adds another $1.17 billion.

Annualized capital costs total approximately $7.6 billion, far exceeding the roughly $900 million in annual operating expenses.

Why AI Servers Cost So Much

Epoch’s model uses NVIDIA GB200 NVL72 rack-scale systems, each priced above $3 million. Their advanced AI chips, high-bandwidth memory, and specialized networking help explain the large hardware bill.

Replacement cycles matter too. The model assumes five years for IT equipment but 14 years for the facility, making hardware refreshes particularly consequential.

Why Electricity Still Matters

Energy is the biggest operating expense at $594 million a year, even though it represents only about 7% of modeled annual costs. That distinction matters for utilities serving increasingly power-hungry campuses.

Meanwhile, data centers have already contributed to higher wholesale electricity prices in several U.S. regions, according to a separate study.

Related Topics: #technology #energy #infrastructure #computing #electricity #artificial intelligence #ai #nvidia #utilities #data centers #Capital Expenditure

You may also like

Subscribe

Share
Next storyAnker’s 100W universal travel charger is down to $60, its lowest price yet
Newsletter

Get the latest news delivered to your inbox.

Related articles