Mongolia and Entrée aim to settle Shivee Tolgoi and Javkhlant licences by 31 March 2027

The key question is whether the state takes up to 34% of Entrée LLC or a royalty instead; Parliament has the final say.

This story was prepared automatically by software.

A covered conveyor at the Oyu Tolgoi mine. Image: Entrée Resources
A covered conveyor at the Oyu Tolgoi mine. Image: Entrée Resources

Canada's Entrée Resources and the Government of Mongolia have agreed to work towards a deal by 31 March 2027 on the Shivee Tolgoi and Javkhlant licences covering Oyu Tolgoi's Hugo North Extension, The Northern Miner reported on 27 November. Mongolian outlets including Press Center also covered the announcement in detail.

Stake or royalty

The main question is whether the state takes a stake of up to 34% in Entrée LLC, the subsidiary that holds the two licences, or accepts a royalty instead. Parliament has the final say. In March, Entrée offered to pay the state a royalty on the gross sales value of its share of concentrate; the company said it received no formal response and will prepare a revised offer.

Under terms the two sides agreed on 9 and 10 November, they can extend talks beyond March by mutual consent. The next round of negotiations is scheduled for January.

Underground development on hold

The unresolved licences have held up underground development on the Shivee Tolgoi area. According to The Northern Miner, crews had completed about 230 equivalent metres of lateral development on Shivee Tolgoi by 30 May 2025, a week before the work was paused. Mine operator Oyu Tolgoi LLC needs the licences in its name before it can resume development there. Entrée holds a 20% carried interest in Hugo North Extension.

The licence transfer also requires tax payment certificates, but the tax authority told Entrée LLC it could not issue them because the documents supporting the licence valuations were incomplete.

New drill results

The company also released assays from seven underground holes drilled at Hugo North Extension between 2023 and 2026. Hole UGD1025A cut 125.3 metres grading 1.28% copper, 0.27 grams of gold and 3.18 grams of silver per tonne from 362.7 metres downhole.

Mongolia owns 34% of Oyu Tolgoi LLC and Rio Tinto owns 66%. Rio Tinto expects the open pit and underground mine together to produce an average of 500,000 tonnes of copper a year from 2028 to 2036.

Sources: The Northern Miner, Press Center